Works on the construction site of CC STOS, despite unfavorable weather conditions, take place according to the adopted schedule.
– We are in the process of performing the so-called building shell – says Dominik Kardynał, construction manager from the NDI group. – We have completed the excavation support, we also make sanitary and electrical installations. The lower foundation slab of the ‘-2’ level is also ready, as well as the walls and ceilings above the ‘-1’ level, and now we are working on the ‘0’ level ceilings. This year winter does not help us, but we manage to implement almost all the planned works.
Currently, builders are working on the construction of the deepest part of the building, i.e. underground garages. In the coming weeks, the contractor plans to build the last ‘0’ ceiling above the garage part and will carry out further works planned in the construction schedule.