Project timeline

L
01.03.2023

planned final investment commissioning

L
08.03.2022

planned completion of works related to architecture and equipment

L
02.12.2021

completion of work ceilings / roofs

L
15.10.2021

topping out ceremony
see more →

L
18.02.2021

Signing the foundation act and laying the foundation stone for the construction of the CC STOS at Gdańsk University of technology
see more →

L
02-03.2021

groundworks

L
30.11.2020

due to the increase in investment costs, an annex was signed to the agreement regarding the increase in financing

L
11.09.2020

official handover of the construction site
see more →

L
08.09.2020

signing a contract with the contractor, consortium NDI Sp. z o.o. and NDI Sopot SA based in Sopot

L
04.12.2019

tender results

L
06.05.2019

signing a contract for the CC STOS project implementation

L
2018

application approval for project financing

L
01.02.2017

acceptance of the proposal for the creation of CC STOS and commencement of the construction project implementation

L
2016

preliminary plans for the establishing CC STOS in the territorial contract