Project timeline
01.03.2023
planned final investment commissioning
08.03.2022
planned completion of works related to architecture and equipment
02.12.2021
completion of work ceilings / roofs
15.10.2021
topping out ceremony
see more →
18.02.2021
Signing the foundation act and laying the foundation stone for the construction of the CC STOS at Gdańsk University of technology
see more →
02-03.2021
groundworks
30.11.2020
due to the increase in investment costs, an annex was signed to the agreement regarding the increase in financing
11.09.2020
official handover of the construction site
see more →
08.09.2020
signing a contract with the contractor, consortium NDI Sp. z o.o. and NDI Sopot SA based in Sopot
04.12.2019
tender results
06.05.2019
signing a contract for the CC STOS project implementation
2018
application approval for project financing
01.02.2017
acceptance of the proposal for the creation of CC STOS and commencement of the construction project implementation
2016
preliminary plans for the establishing CC STOS in the territorial contract