{"id":242269,"date":"2021-03-30T15:47:29","date_gmt":"2021-03-30T15:47:29","guid":{"rendered":"https:\/\/stos.gda.pl\/budowa-ck-stos-zgodnie-z-harmonogramem\/"},"modified":"2021-10-18T10:09:25","modified_gmt":"2021-10-18T10:09:25","slug":"budowa-ck-stos-zgodnie-z-harmonogramem","status":"publish","type":"post","link":"https:\/\/stos.gda.pl\/en\/budowa-ck-stos-zgodnie-z-harmonogramem\/","title":{"rendered":"Construction of CC STOS according to schedule"},"content":{"rendered":"
\u2013 We are in the process of performing the so-called building shell \u2013 says Dominik Kardyna\u0142, construction manager from the NDI group. \u2013 We have completed the excavation support, we also make sanitary and electrical installations. The lower foundation slab of the \u2018-2\u2019 level is also ready, as well as the walls and ceilings above the \u2018-1\u2019 level, and now we are working on the \u20180\u2019 level ceilings. This year winter does not help us, but we manage to implement almost all the planned works.<\/p>\n
Currently, builders are working on the construction of the deepest part of the building, i.e. underground garages. In the coming weeks, the contractor plans to build the last \u20180\u2019 ceiling above the garage part and will carry out further works planned in the construction schedule.<\/p>\n
<\/p>\n